Forced sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer and applying a pressure of 5 psi (34.5 kPa) greater than the pump rating, and maintaining such pressure for 15 minutes.

Related Code Sections

312.7 General Regulations, Forced Sewer Test
Forced sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer and applying a pressure ...
312.7 General Regulations, Forced Sewer Test
Forced sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer and applying a pressure ...
312.7 General Regulations, Forced Sewer Test
Forced sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer and applying a pressure ...
P2503.4 Plumbing Administration, Building Sewer Testing
15 minutes. The building sewer shall be watertight at all points. A forced sewer test shall consist of pressurizing the piping to a pressure ...
312.6 General Regulations, Gravity Sewer Test
Gravity sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer, filling the building ...