// CODE SNIPPET
1405.2.2 Final Piping Inspection
JUMP TO FULL CODE CHAPTER
This inspection
shall be made after piping authorized by the permit has
been installed and after portions thereof that are to be covered
or concealed are so concealed. This inspection shall
include a pressure test, at which time the piping shall
stand a pressure of not less than one-and-one-half times
the maximum designed operating pressure where
hydraulic testing is conducted or 110 percent where testing
is conducted pneumatically. Test pressures shall be
held for a length of time satisfactory to the Authority Having
Jurisdiction, but in no case for less than 30 minutes
with no perceptible drop in pressure. HPM drain, waste,
and vent piping shall be tested in accordance with the
plumbing code. Tests shall be made in the presence of the
Authority Having Jurisdiction. Necessary apparatus for
conducting tests shall be furnished by the permit holder.
Related Code Sections
1203.3.2 Fuel Gas Piping, Final Piping Inspection
This inspection shall
be made after piping authorized by the permit has been
installed and after portions thereof that are to be covered
or concealed ...
California Plumbing Code 2016 > 12 Fuel Gas Piping > 1203.0 Inspection > 1203.3 Type of Inspections > 1203.3.2 Final Piping Inspection
1203.3.2 Fuel Gas Piping, Final Piping Inspection
This inspection shall be made after piping authorized by the permit has
been installed, and after portions, thereof that are to be covered ...
California Plumbing Code 2019 > 12 Fuel Gas Piping > 1203.0 Inspection > 1203.3 Type of Inspections > 1203.3.2 Final Piping Inspection
1303.3.2 Fuel Gas Piping, Final Piping Inspection
This inspection shall
be made after piping authorized by the permit has been
installed and after portions thereof that are to be covered
or concealed ...
California Mechanical Code 2016 > 13 Fuel Gas Piping > 1303.0 Inspection > 1303.3 Type of Inspections > 1303.3.2 Final Piping Inspection
1303.3.2 Fuel Gas Piping, Final Piping Inspection
This inspection
shall be made after piping authorized by the permit has
been installed and after portions thereof that are to be covered or concealed ...
California Mechanical Code 2019 > 13 Fuel Gas Piping > 1303.0 Inspection > 1303.3 Type of Inspections > 1303.3.2 Final Piping Inspection
1405.2.2 Process Piping, Final Piping Inspection
This inspection shall
be made after piping authorized by the permit has been
installed and after portions thereof that are to be covered
or concealed ...
California Mechanical Code 2016 > 14 Process Piping > 1405.0 Inspections > 1405.2 Required Inspections > 1405.2.2 Final Piping Inspection