§40-12 Examination and Approval of Applications
JUMP TO FULL CODE CHAPTER
(a) Applications, when filed, shall be processed in the usual manner and forwarded to the inspectors of plumbing.
(b) Applications calling for the installation of gas-fueled space and water heaters shall be expedited and may be taken out of turn, except that they shall be processed in the order in which they were received. They shall be examined for compliance with these rules and all other laws and regulations applicable to such installations. If any chimney or metal stack is to be installed, examiners shall check such construction for compliance with Subchapter 15 of Chapter 1 of Title 27 of the Administrative Code (Building Code). They shall require that the foundation shall be carried not less than four feet below the surface of the ground, and that the soil on which it is built to be not overloaded. They shall require that new chimneys be strapped to the existing walls.
(c) Only applications calling for the installation of gas-fueled space or water heaters, approved by the Department of Buildings, specifying the make and model shall be approved. All such gas appliances shall be of types approved also by the American Gas Association. However, where an owner desires to continue to use any gas appliance installed in a multiple dwelling prior to December 9, 1955, clearly shows on the plan the data required by 1 RCNY §40-11(f) and prominently marks the appliances that have not been approved by the Department of Health, the application may be conditionally approved pending the approval of the appliances by the Department of Health.
Related Code Sections
§28-112.6.1 Administration, Withdrawal of Work Permit Applications
an application for construction document approval is withdrawn prior to the commencement of examination of the application all but forty dollars of the deposit fee ...
NYC General Admin. Provisions 2014 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.1 Withdrawal of Work Permit Applications
§28-112.6.1 Administration, Withdrawal of Work Permit Applications
If an application for construction document approval is withdrawn prior to the commencement of examination of the application all but forty dollars ...
NYC General Admin. Provisions 2008 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.1 Withdrawal of Work Permit Applications
§28-104.2.1.5 Administration, Applicant Requirement
on the result of the evaluation and inspections, secures department approval after examination of construction and other related documents submitted ...
NYC General Admin. Provisions 2014 > 1 Administration > 104 Construction Documents > *§28-104.2 Application for Approval of Construction Documents > **§28-104.2.1 Less Than Full Examination of Applications for Construction and Related Document Approval > §28-104.2.1.5 Applicant Requirement
§28-112.6.2 Administration, Withdrawal of Cranes and Derricks Applications
its examination, whether or not the application has been approved no part of the fee shall be returned to the applicant ...
NYC General Admin. Provisions 2014 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.2 Withdrawal of Cranes and Derricks Applications
§28-112.6.2 Administration, Withdrawal of Cranes and Derricks Applications
is withdrawn after the department has performed its examination, whether or not the application has been approved no part of the fee shall be returned ...
NYC General Admin. Provisions 2008 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.2 Withdrawal of Cranes and Derricks Applications