// CODE SNIPPET
§28-308.7.1.2 Early Compliance Audit Completed After the Effective Date of This Article
JUMP TO FULL CODE CHAPTER
An early compliance audit completed after the effective date of this article shall meet the following additional criteria:
- The audit shall be performed by or under the supervision of a registered design professional and shall meet the requirements of the Level II Energy Survey and Analysis of the 2004 edition of Procedures for Commercial Building Energy Audits published by ASHRAE;
- The auditing team shall include an individual who is one of the following:
- A NYSERDA approved Flex Tech contractor;
- A Certified Energy Manager (CEM) or Certified Energy Auditor (CEA), certified by the Association of Energy Engineers (AEE);
- A High-Performance Building Design Professional (HPBD) certified by ASHRAE; or
- For audits of multifamily residential buildings only, a Multi-family Building Analyst (MFBA), certified by the Building Performance Institute (BPI), or have such other qualification or certification as determined by the department;
- An individual with at least three years of professional experience performing energy audits on buildings larger than 50,000 gross square feet (4645 m2) shall be a member of the auditing team;
- The building's operations and maintenance staff shall be consulted at the start of and during the audit process; and
- The registered design professional performing or supervising the audit shall certify that the audit satisfies the criteria of this section.
Related Code Sections
§28-308.7.1.2 Maintenance of Buildings, Early Compliance Audit Completed After the Effective Date of This Article
An early compliance audit completed after the effective date of this article shall meet the following additional criteria:
The audit shall ...
NYC General Admin. Provisions 2014 > 3 Maintenance of Buildings > 308 Energy Audits and Retro-Commissioning of Base Building Systems > §28-308.7 Early Compliance > §28-308.7.1 Early Compliance Energy Audit Report > §28-308.7.1.2 Early Compliance Audit Completed After the Effective Date of This Article
*§28-308.7.1.2 Maintenance of Buildings, Early Compliance Audit Completed After the Effective Date of This Article
An early compliance audit completed after the effective date of this article shall meet the following additional criteria: 1. The audit ...
NYC General Admin. Provisions 2008 > 3 Maintenance of Buildings > 308 *Energy Audits and Retro-Commissioning of Base Building Systems > *§28-308.7 Early Compliance > *§28-308.7.1 Early Compliance Energy Audit Report > *§28-308.7.1.2 Early Compliance Audit Completed After the Effective Date of This Article
*§28-308.7.1 Maintenance of Buildings, Early Compliance Energy Audit Report
An early compliance audit completed after the effective date of this article shall meet the following additional ...
NYC General Admin. Provisions 2008 > 3 Maintenance of Buildings > 308 *Energy Audits and Retro-Commissioning of Base Building Systems > *§28-308.7 Early Compliance > *§28-308.7.1 Early Compliance Energy Audit Report
*§28-308.7.2 Maintenance of Buildings, Early Compliance Retro-Commissioning
a. Retro-commissioning shall be acceptable for early compliance if it is completed after the effective date of this article and meets the following ...
NYC General Admin. Provisions 2008 > 3 Maintenance of Buildings > 308 *Energy Audits and Retro-Commissioning of Base Building Systems > *§28-308.7 Early Compliance > *§28-308.7.2 Early Compliance Retro-Commissioning
§28-308.7.2 Maintenance of Buildings, Early Compliance Retro-Commissioning
A retro-commissioning shall be acceptable for early compliance if it is completed after the effective date of this article and meets the following ...
NYC General Admin. Provisions 2014 > 3 Maintenance of Buildings > 308 Energy Audits and Retro-Commissioning of Base Building Systems > §28-308.7 Early Compliance > §28-308.7.2 Early Compliance Retro-Commissioning