The commissioner shall not issue a permit for a building for at least one year following the date of a determination by the commissioner that work has been performed without a permit in such building and such building was occupied at the time such work was being performed. Such denial shall not apply where a dwelling unit within such multiple dwelling is owned as a condominium or held by a shareholder of a cooperative corporation under a proprietary lease.
Exceptions:
  1. Where the issuance of such permit is necessary to correct an outstanding violation of this code, the New York city housing maintenance code or any other applicable provisions of law or rule.
  2. Where the issuance of such permit is necessary to perform work to protect public health and safety.
  3. For a portion of a property occupied by a tenant who is not an owner of such property or responsible for any existing violations in such property.
  4. Where a property was the subject of an in rem foreclosure judgment in favor of the city and was transferred by the city to a third party pursuant to section 11-412.1 of the administrative code.
  5. Where a property is the subject of a court order appointing an administrator pursuant to article 7-a of the New York state real property actions and proceedings law in a case brought by the department of housing preservation and development.
  6. Where a property is the subject of a loan provided by or through the department of housing preservation and development or the New York city housing development corporation for the purpose of rehabilitation that has closed within the five years preceding the application for such permit.
  7. For a property where the department of housing preservation and development or the New York city housing development corporation notifies the commissioner that the permit is required in connection with the implementation of a program of such department or corporation.
*Section 28-105.1.5 was added by Local Law 114 of 2019. This law has an effective date of December 5, 2019.

Related Code Sections

§28-105.1 Administration, General
been performed without a permit in such building and such building was occupied at the time such work was being performed. Such denial shall not apply ...
§28-105.1 Administration, General
by the commissioner that work has been performed without a permit in such building and such building was occupied at the time such work was being performed ...