Section A-303 Demolition and Relocation of Structures
JUMP TO FULL CODE CHAPTER
Before a structure is demolished or removed, the Demolition Contractor licensed pursuant to § 9-1008 of The Philadelphia Code responsible for the demolition shall notify all utilities having service connections within the structure such as water, electric, gas, sewer and other connections. Service connections and appurtenant equipment, such as meters and regulators shall be removed or sealed and plugged in a safe manner.
Upon submittal of an application for a permit for the demolition of a structure, the department shall provide a notice to the Demolition Contractor to be posted prior to the demolition of the structure. The Demolition Contractor shall post such notice on the structure to be demolished.
Upon issuance of the building permit for the demolition, and in addition to the notification requirements for contractors established in this Section and the Building Code, the department is authorized to distribute an informational bulletin indicating that the City or owner intends to demolish said structure. The department shall distribute the informational bulletin to the properties located within a 100 foot radius of the subject property.
The requirement to distribute an informational bulletin shall not create any actionable right for any resident or owner of the subject property or any neighboring property.
Exceptions:
- In the event of an emergency which requires immediate action to protect the health or safety of the public, which shall include any time the Department has served notice of a requirement to demolish an imminently dangerous structure under Section PM-110.2 of this Title and demolition is carried out within 10 days of service by the Department of the notice requiring demolition; provided that the Department distributes the informational bulletin to any property abutting the property on which a structure is to be demolished.
- When the structure has been posted as required by Section 14-303(13) of The Philadelphia Code.
- When the structure has been the subject of a variance granted by the Zoning Board of Adjustment.
The notice shall be posted by the Demolition Contractor on each street frontage of the premises with which the notice is concerned. Posted notices shall remain until demolition of the structure, which shall not commence less than 21 days from the date of the initial posting of the notice.
Such posted notice shall be clearly visible to the public. All notices shall contain the date on which the permit application for demolition was submitted to the Department.
No person shall remove such notice prior to the approved date on which demolition is permitted to commence, unless the owner notifies the department that the structure will not be demolished and the permit has been revoked by the department upon such request, in which case, the Demolition Contractor shall remove the notice.
Any Demolition Contractor who violates the provisions of this Section shall be subject to penalties as prescribed in Chapter 6.
The Department shall include in any informational bulletin distributed pursuant to this Section all of the following: education material explaining the inherent safety risks of demolition; contractor obligations regarding party walls; information concerning shoring and bracing of walls; waterproofing and enclosure of breaches for interior walls that become exterior walls, and other required finishings.
A demolition permit shall be valid only in connection with work performed by the licensed Demolition Contractor identified on the permit. A Demolition Contractor that seeks to perform demolition work under a permit identifying another contractor must obtain an amendment of such permit that authorizes work by the new Demolition Contractor.
Before any structure which has been moved is occupied, the structure and mechanical equipment shall be inspected for safe use and operation and for compliance with applicable provisions of this code and the technical codes.
Related Code Sections
Section A-303 Permits, Demolition and Relocation of Structures
Before a structure is demolished or removed, the Demolition Contractor licensed pursuant to § 9-1008 of The Philadelphia Code responsible ...
A-303.2.1 Permits, Location and Time
shall remain until demolition of the structure, which shall not commence less than 21 days from the date of the initial posting of the notice ...
Philadelphia Administrative Code > 3 Permits > A-303 Demolition and Relocation of Structures > A-303.2 Posting and Notice > A-303.2.1 Location and Time
A-303.2.2 Permits, Content
Such posted notice shall be clearly visible to the public. All notices shall contain the date on which the permit application for demolition ...
Philadelphia Administrative Code > 3 Permits > A-303 Demolition and Relocation of Structures > A-303.2 Posting and Notice > A-303.2.2 Content
A-303.2.4 Permits, Penalties
Any Demolition Contractor who violates the provisions of this Section shall be subject to penalties as prescribed in Chapter 6 ...
Philadelphia Administrative Code > 3 Permits > A-303 Demolition and Relocation of Structures > A-303.2 Posting and Notice > A-303.2.4 Penalties
A-303.2.5 Permits, Additional Posting and Notice
the inherent safety risks of demolition; contractor obligations regarding party walls; information concerning shoring and bracing of walls ...
Philadelphia Administrative Code > 3 Permits > A-303 Demolition and Relocation of Structures > A-303.2 Posting and Notice > A-303.2.5 Additional Posting and Notice