During the curing periods specified herein, shotcrete shall be maintained above 40°F (4°C) and in moist condition.
Shotcrete shall be kept continuously moist for 24 hours after shotcreting is complete or shall be sealed with an approved curing compound.
Natural curing shall not be used in lieu of that specified in this section unless the relative humidity remains at or above 85 percent, and is authorized by the registered design professional and approved by the building official.
Related Code Sections
1908.9 Concrete, Curing
During the curing periods specified herein, shotcrete shall be maintained above 40°F (4°C) and in moist condition ...
1908.9 Concrete, Curing
During the curing periods specified herein, shotcrete shall be maintained above 40°F (4°C) and in moist condition ...
2512.8.2 Gypsum Board, Gypsum Panel Products and Plaster, Curing
Curing of the first coat is permitted to be omitted and the second coat shall be cured as set forth in ASTM C926 and Table 2512.6 ...
Building Code 2018 of Utah > 25 Gypsum Board, Gypsum Panel Products and Plaster > 2512 Exterior Plaster > 2512.8 Alternate Method of Application > 2512.8.2 Curing
2512.8.2 Gypsum Board, Gypsum Panel Products and Plaster, Curing
Curing of the first coat is permitted to be omitted and the second coat shall be cured as set forth in ASTM C926 and Table 2512.6 ...
Building Code 2015 of Utah > 25 Gypsum Board, Gypsum Panel Products and Plaster > 2512 Exterior Plaster > 2512.8 Alternate Method of Application > 2512.8.2 Curing
R702.2.2.2 Wall Covering, Curing
The finish coat for two-coat cement plaster shall not be applied sooner than 48 hours after application of the first coat. For three-coat cement ...