// CODE SNIPPET

Section 3319 Cranes and Derricks

NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks
JUMP TO FULL CODE CHAPTER
buildings bulletin
Linked Resources Available

This section has been clarified by a buildings bulletin issued by the Department of Buildings.

Learn more in the Linked Resources panel on the right.

3319.1 Scope

The construction, installation, inspection, maintenance and use of cranes and derricks shall be in conformance with the requirements of this section, Section 3316, and with rules promulgated by the commissioner.

*3319.2 Personnel

Personnel shall comply with Sections 3319.2.1 through 3319.2.3.

*3319.2.1 Hoisting machine operators

The hoisting machine operator shall be licensed as required by Chapter 4 of Title 28 of the Administrative Code.

*3319.2.2 Riggers

Rigging work must be supervised in accordance with Section 3316.9.1 and where required, riggers must be licensed in accordance with Chapter 4 of Title 28 of the Administrative Code.

*3319.2.3 Lift directors

Lift directors shall be designated, and perform the duties assigned to them, in accordance with rules promulgated by the commissioner. Such duties shall include, but not be limited to, ensuring compliance with approved plans, traffic and pedestrian controls, and weather restrictions.

*Section 3319.2 was amended by Local Law 14 of 2018. This law has an effective date of December 31, 2017.

3319.3 Requirements

No owner or other person shall authorize or permit the operation of any crane or derrick without a certificate of approval, a Certificate of Operation and a Certificate of On-site Inspection.

Exceptions:

1. The requirements of this section shall not apply to excavating or earth-moving equipment, except cranes used with clamshells.

2. The requirements of this section shall not apply to cranes or derricks performing an emergency use pursuant to the lawful order of the head of any department.

3. The requirements of this section shall not apply to mobile cranes, including jibs and any other extensions to the boom not exceeding 50 feet (15 240 mm) in length and with a manufacturer's rated capacity of 3 tons (2722 kg) or less.

4. The requirements of this section shall not apply to mobile cranes, including jibs and any other extensions, exceeding 50 feet (15 240 mm) but not exceeding 135 feet (41 148 mm) in length, and with a manufacturer's rated capacity of 3 tons (2722 kg) or less, except that a Certificate of Operation, as provided for in Section 3319.5, shall be required. The requirement for a Certificate of Operation shall not apply to such a crane used exclusively as a man basket. The commissioner may, by rule, exempt other mobile cranes of limited size from any or all requirements of this section.

5. The requirements of this section shall not apply to hoisting machines permanently mounted on the bed of material delivery trucks that are used exclusively for loading and unloading such trucks, provided that the length of boom does not exceed the length of the truck bed by more than 5 feet (1524 mm) and that any material transported thereon shall not be raised more than 2 feet (610 mm) in the unloading process. Operators of such equipment shall be exempt from licensing requirements described in Chapter 4 of Title 28 of the Administrative Code.

6. The requirements of this section shall not apply to cranes or derricks used in industrial or commercial plants or yards not used for the construction of the facility. Floating cranes, floating derricks, and cranes and derricks used on floating equipment shall also be exempt from the requirements of this section. Operators of such equipment shall be exempt from the licensing requirements described in Chapter 4 of Title 28 of the Administrative Code.

7. The requirements of this section shall not apply to augurs, churn-drills and other drilling equipment not used for hoisting any objects. Operators of such equipment shall be exempt from the licensing requirements described in Chapter 4 of Title 28 of the Administrative Code.

8. The requirements of this section shall not apply to derricks having a maximum rated capacity not exceeding 1 ton (907 kg).

9. The requirements of this section shall not apply to mechanic's truck with a hoisting device when used in activities related to the maintenance and repair of construction-related equipment.

10. The requirements of this section shall not apply to articulating boom cranes that do not have an integral hoisting mechanism, and that are used exclusively for loading and unloading of trucks or trailers, provided that the length of boom does not exceed 135 feet (41 148 mm) and that any material transported thereon shall not be raised more than 100 feet (30 480 mm) in the unloading process. Operators of such equipment shall be exempt from licensing requirements described in Chapter 4 of Title 28 of the Administrative Code.

3319.4 Certificate of Approval

buildings bulletin
Linked Resources Available

This section has been clarified by a buildings bulletin issued by the Department of Buildings.

Learn more in the Linked Resources panel on the right.
Certificates of Approval shall comply with the following:

1. The manufacturer, owner, or designated representative of a crane or derrick for which a Certificate of Approval is sought shall file an application for such Certificate of Approval and provide such information as set forth in rules promulgated by the commissioner.

2. Upon the department's approval of the application described in Item 1 above, the department shall issue a Certificate of Approval for the equipment and an approval of the submitted load rating chart.

3. A new Certificate of Approval shall be required when a crane or derrick is modified or altered to increase the boom length, jibs or any extensions to the boom beyond the maximum approval length or when the load ratings are increased.

3319.5 Certificate of Operation

Certificates of Operation shall comply with the following:

1. The commissioner shall issue the initial Certificate of Operations for the crane or derrick with Certificate of Approval upon satisfactory inspection and test indicating that such crane or derrick is in a safe operating condition. The initial Certificate of Operation shall expire 1 year from the date of issuance.

2. The owner of a crane or derrick covered by the Certificate of Operation shall renew the Certificate of Operation each year.

3. If the owner of the covered crane or derrick applies for renewal of a certificate of operation within not more than 60 nor less than 30 days prior to the date of its expiration, such owner may continue to use the covered crane or derrick until the department grants or denies a new certificate.

4. When a crane or derrick configuration is changed to increase the boom length, jibs or any extensions to the boom beyond the maximum approval length or when the load ratings are increased, a new Certificate of Operation shall be required. In such a case, the crane or derrick may not be operated until the new Certificate of Operation is obtained.

5. An application for a new certificate of operation shall be submitted when attachments that affect the stability or structure of the crane or derrick are added. Calculations and load rating charts as required by rules promulgated by the commissioner shall be submitted with the renewal request.

3319.6 Certificate of On-Site Inspection

Certificates of on-site inspection shall comply with the following:

1. The equipment user, or his or her designated representative, shall obtain a Certificate of On-site Inspection for the use of any crane or derrick used for construction or demolition purposes at each job site. Such application for the Certificate of On-site Inspection shall include information set forth in rules promulgated by the commissioner.

2. Upon approval of the application, a copy of such approval shall be given to the applicant. It shall be unlawful to operate the equipment that is the subject of the approval until it has been inspected and found to be satisfactory by the department as set forth in rules promulgated by the commissioner. Upon inspection and a finding of satisfactory compliance, the approval shall be deemed a Certificate of On-site Inspection, which shall expire one year from the date of issuance. A Certificate of On-site Inspection may be renewed in accordance with rules promulgated by the commissioner.

3. The Certificate of On-site Inspection is valid only if the conditions and statements contained in the approved application are complied with, and the crane or derrick is operated in conformance with the provisions of this section and the rules applicable thereto.

4. A Certificate of On-site Inspection is not required for cranes or derricks performing work exempted from such requirement by rules promulgated by the commissioner.

3319.7 Temporary Certificates

The commissioner may issue temporary Certificates of Approval, operation and on-site inspection for any crane or derrick during the pendency of an application for Certificates of Approval and operation upon inspection and upon such analysis and testing as the commissioner may deem necessary. The commissioner may revoke such temporary certificates if the application is denied.

3319.8 Special Provisions for Tower and Climber Cranes

Tower and climber cranes shall comply with the following requirements:

*3319.8.1 Plan for the Erection, Jumping, Climbing, and Dismantling of Tower or Climber Cranes

An erection, jumping, climbing and dismantling plan for tower or climber cranes, other than truck and crawler mounted tower cranes, shall be submitted to the department by a licensed engineer. The plan must be prepared by a licensed engineer in conjunction with a licensed rigger and must be in compliance with the manufacturer's recommendation for erection, jumping, climbing, or dismantling of the specific crane where such manufacturer's recommendations exist. The plan must be filed with the certificate of on-site inspection application as required by Section 3319.3. No erection, jumping, climbing, or dismantling of a tower or climber crane shall take place without the prior issuance of a certificate of on-site inspection by the cranes and derricks unit. The plan shall include the following:

1. Identification of the equipment proposed to be used; including all machines proposed to be used in the erection or dismantling;

2. A detailed identification of the assemblies and components required for the erection and dismantling of the equipment;

3. Location of the equipment, sidewalk sheds (or Department of Transportation street closing permits, if applicable), surrounding buildings, protection for their roofs and the pick-up points, loads, and radius of swing of all loads. In addition, the safe load from the approved load radius chart shall be submitted for lift radius;

4. A weight list of all assemblies and components proposed to be lifted. Components are to be clearly marked with their weight painted on the assembly or stamped on metal tags attached to the assembly. The manufacturer of the climber or tower crane shall certify the weight of assemblies and components. Alternately, in lieu of painted weight markings or metal tags, or when the manufacturer's certification is not available, the licensed engineer applicant shall certify an erection, jumping, climbing or dismantling weight list indicating how such weights were determined;

5. The center of gravity of all asymmetrical components shall be located and shown;

6. A sequence of operation detailing the erection, jumping, climbing, and dismantling, along with the rigging materials to be used in such operations;

7. The certification of the calibration as required in Item 6 of Section 3319.8.8;

8. Cranes or derricks located either within the lot line or on the street and used to erect, jump, climb, or dismantle a tower or climber crane shall be indicated;

9. The names and contact information of the licensed master, climber or tower crane rigger, and the rigger foreman along with the name and contact information of the company performing the erection, dismantling, climbing and/or jumping work.

*Section 3319.8.1 was amended by Local Law 14 of 2018. This law has an effective date of December 31, 2017.

*3319.8.2 Safety Coordination Meeting

The general contractor must hold a safety coordination meeting prior to the initial erection, as well as the dismantling or initial jump down, of a climber or tower crane. No work related to the erection, climbing, jumping or dismantling of the tower or climber crane may be performed without the safety coordination meeting having taken place. The following parties must be present at the safety coordination meeting:

1. General contractor or designee;

2. Professional engineer of record for the crane or designee;

3. Licensed master, tower or climber crane rigger and rigger foreman;

4. Site safety manager or coordinator, if required for the job by Chapter 33 of the code;

5. Licensed crane operator and oiler; and

6. Any other parties the department deems necessary.

*Section 3319.8.2 was amended by Local Law 14 of 2018. This law has an effective date of December 31, 2017.

*3319.8.3 Pre-Jump Safety Meeting

The general contractor must coordinate a pre-jump safety meeting no more than 24 hours prior to each instance of a tower or climber crane jump or climb. No work related to the jumping or climbing of the tower or climber crane may be performed without the pre-jump safety meeting having taken place. The following parties must be present at the pre-jump safety meeting:

1. General contractor or designee;

2. Licensed master, tower or climber crane rigger and rigger foreman;

3. Site safety manager or coordinator, if required for the job by Chapter 33 of the building code;

4. Licensed crane operator and oiler;

5. "Jumping" crew and back-up personnel;

6. Flagman/woman where required;

7. Signalman/woman and communications personnel; and

8. Any other parties the department deems necessary.

*Section 3319.8.3 was amended by Local Law 14 of 2018. This law has an effective date of December 31, 2017.

3319.8.4 Department Notification

3319.8.4.1 Meeting Notifications

The general contractor must notify the department at least 48 hours in advance of any safety coordination meeting or pre-jump safety meeting. No work related to the erecting, jumping, climbing, or dismantling of the tower or climber crane is to be performed without prior notice of the meeting having been given to the department.

3319.8.4.2 Time Schedule

A time schedule including date and time of day that the erection, jumping, climbing, or dismantling is proposed to take place shall be provided as soon as it is known by the general contractor.

3319.8.5 Safety Coordination and Pre-Jump Safety Meeting Topics

The following topics are to be covered during safety coordination and pre-jump safety meetings:

1. Scope of work;

2. Roles and responsibilities;

3. Rigging to be used and the specific sequence of operations;

4. Inspection of all rigging equipment, materials, and tools prior to work;

5. Review of all equipment, including but not limited to, collars, ties, and bolts;

6. Permit validity;

7. Qualifications and training of personnel;

8. Relevant weather warnings;

9. Compliance with the manufacturer's manual; and

10. Softening mechanisms, if using nylon slings.

3319.8.6 Meeting Log

The general contractor, or his or her designee, and/or the company erecting, jumping, climbing, or dismantling the tower or climber crane shall keep a log on site and available to the department at all times that shall include:

1. The dates and times of all safety coordination meetings and pre-jump safety meetings held;

2. The names, titles, and company affiliations of all those present at the meetings;

3. A summary of what was discussed during each meeting, including specific tasks and the name of the person to whom they were assigned;

4. A list of the decisions made at the meeting; and

5. Certification of worker training pursuant to Section 3319.10.

3319.8.7 Inspection and Certification by the Engineer of Record

Prior to jumping or climbing a tower or climber crane, the engineer of record for the crane must provide the department with a certified, signed, and sealed report stating that:

1. He or she (or his or her designee) has inspected the crane installation prior to the pre-jump safety meeting, and providing the date of inspection;

2. He or she has found no hazardous conditions during the crane inspection or any other condition within his or her purview that adversely affects the safety of erection, dismantling, climbing, or jumping operations;

3. The crane is installed according to the plans approved by the department as well as in accordance with the manufacturer's specifications to the extent applicable; and

4. The appropriate technical testing records for the crane, including torque, plumb, and magnetic particle or other appropriate reports comply with safety requirements and with the manufacturer's specifications.

*3319.8.8 Erection, Jumping, Climbing, and Dismantling Operations

The erection, jumping, climbing, and dismantling operations for tower and climber cranes shall be subject to the following requirements:

1. The licensed master, tower or climber crane rigger, and the rigger foreman, shall be present at the job site during erection, jumping, climbing, and dismantling of the tower or climber crane;

2. Cranes or derricks located either within the lot line or on the street, and used to erect, jump, climb, or dismantle tower or climber cranes, shall be subject to certificate of on-site inspection requirements;

3. A load radius chart approved by department shall be posted in the cabin of the crane;

4. The approved erection, jumping, climbing, or dismantling procedure and sequence, with weights of assemblies and components clearly marked, shall be given by the equipment user to the licensed operator of the crane or derrick and to the rigger prior to commencement of the work;

5. No tower or climber crane shall be placed, erected or disassembled in any roadway, sidewalk, or street unless a permit is first obtained from the New York City Department of Transportation;

6. All accepted or approved installed safety devices on a crane involved in the erection, jumping, climbing, or dismantling procedure shall have been calibrated within the time period provided by department rules or manufacturer's specifications; and

7. The safety devices of the tower or climber crane shall be inspected by the licensed crane operator as part of the inspection procedure.

*Section 3319.8.8 was amended by Local Law 14 of 2018. This law has an effective date of December 31, 2017.

3319.9 Slings

Slings shall be used in accordance with the following requirements and any rules promulgated by the commissioner.

3319.9.1 Use of Nylon Slings in Conjunction With Climber or Tower Crane Erection, Jumping, Climbing, and Dismantling

Nylon slings shall only be used in conjunction with climber or tower crane erection, jumping, climbing, and dismantling if the manufacturer's manual specifically states or recommends the use of nylon slings. Nylon slings shall not be used unless softening mechanisms have been applied to all sharp edges.

3319.9.2 Discarded Rope

Discarded rope shall not be used for slings.

3319.10 Worker Training

3319.10.1 Training Requirements

All workers engaged in the erection, jumping, climbing, rigging, or dismantling of a climber or tower crane, including the licensed rigger and the rigger foreman, shall have satisfactorily completed a department-approved training course of not less than thirty hours. Such course shall, at a minimum, include instruction on fall protection, crane assembly and disassembly, pre-lift planning, weights and materials, the use of slings, lifting/lowering loads, signaling and other proper means of communication with the crane operator, crane and hoist inspections, rigging requirements, and generally how to avoid accidents with cranes and hoists. The commissioner may by rule identify additional types of cranes for which such training is necessary. Any person who, within the three years prior to the effective date of this section, has successfully completed at least a thirty-hour training course need not take a second thirty-hour course, provided such person can provide to the department a dated certificate as set forth in this section evidencing completion of such a training course. Such person shall, however, take a department-approved eight-hour re-certification course within three years of the initial course and every three years thereafter. Successful completion of the training or re-certification course shall be evidenced by a dated certificate issued by the provider of the training or re-certification course. The certificate shall include such information as specified by the department by rule. The certificate, or a valid wallet card version thereof, shall be readily available to the commissioner upon request.

3319.10.1.1 Training Providers

Such training or refresher course shall be conducted (i) pursuant to a registered New York state department of labor training program, or (ii) by a provider approved by the department.

3319.10.2 Certification

Prior to erecting, jumping, climbing or dismantling the climber or tower crane, or other crane type the commissioner specifies by rule, the master, climber or tower crane rigger shall certify in the meeting log, described in Section 3319.8.6, that the rigger foreman and all other members of the "jumping crew" and back-up personnel have satisfactorily completed all training requirements.

*3319.11 Crane location device

No crane operation that requires a certificate of on-site inspection, and other such types of crane operations where identified in rules promulgated by the commissioner, shall commence unless the crane is equipped with a global positioning system, or other similar device, that is approved by the department and capable of transmitting the location of the crane to which it is attached to the department. Where no such system or device has been approved by the department, (i) no crane operation subject to the provisions of this section shall commence until after the department has been notified by the equipment user, in a form and manner approved by the commissioner, of the date upon which the crane will arrive at the site, and (ii) upon the conclusion of the work, the equipment user shall also notify the department, in a form and manner approved by the commissioner, of the date of the departure of the crane from the site.

Exception: Crane operations that utilize tower or climber cranes and require submission of an erection, jumping, climbing and dismantling plan to the department by a licensed engineer.

*Section 3319.11 was added by Local Law 77 of 2017. This law has an effective date of May 1, 2018.

**3319.12 Crane event recorder

No certificate of operation for a crane shall be issued or renewed on or after January 1, 2019, unless the crane is equipped with an event recorder that is supplied by the crane manufacturer, or by a dealer, distributor, vendor, or third-party authorized crane manufacturer.

Exception: Cranes where the manufacturer certifies to the department that an event recorder cannot be installed on the crane due to a technological limitation.

*Section 3319.12 was added by Local Law 79 of 2017. This law has an effective date of January 1, 2019.

**Section 3319.12 was renumbered by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

**3319.12.1 Data to be recorded

At a minimum, the event recorder shall collect the following data:
  1. Crane configuration;
  2. Any overload condition;
  3. Status of limit switches; and
  4. Operator overrides.
*Section 3319.12.1 was added by Local Law 79 of 2017. This law has an effective date of January 1, 2019.

**Section 3319.12.1 was renumbered by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

**3319.12.2 Data to be made available to commissioner upon request

Data collected by the event recorder shall be made available to the commissioner upon request.

*Section 3319.12.2 was added by Local Law 79 of 2017. This law has an effective date of January 1, 2019.

**Section 3319.12.2 was renumbered by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*3319.13 Measuring wind

Wind speed during crane or derrick operations shall be determined in accordance with the requirements of Table 3319.13. Options 1, 2, and 3 in Table 3319.13 shall be in accordance with the requirements of Sections 3319.13.1 through 3319.13.3, respectively.

*Section 3319.13 was added by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*Table 3319.13
Wind measurement requirements for cranes and derricks
Equipment type Allowable options
Option 1:
Anemometer on the
crane or derrick
Option 2:
Anemometer at the
site
Option 3: Nearest
weather station
Certificate of on-site inspection or supervision
by a licensed master rigger required



Crane with lattice boom, jib, or mast
(and not a pile driver or clamshell)



Yes No
(Except may utilize if
anemometer on crane
malfunctions)
No



Crane utilizing only a telescoping boom



Yes Yes Yes


Crane utilizing only an articulating
boom


Yes Yes Yes



Pile driver



Yes Yes Yes



Clamshell




Yes Yes Yes



Derrick



Yes Yes No


A crane, derrick, pile driver, or clamshell that does not
require a certificate of on-site inspection or supervision
by a licensed master rigger

Yes Yes Yes


*Table 3319.13 was added by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*3319.13.1 Option 1: Anemometer on the crane or derrick

An anemometer provided by the crane or derrick manufacturer, or an entity acceptable to such manufacturer, and installed at the top of the boom or at the location specified by such manufacturer. The anemometer must measure a 3-second gust wind. A real time display of the anemometer must be available to the hoisting machine operator in the crane cab or at the operator's station. Such anemometer is to be considered an operational aid and must be checked prior to each shift as required by department rules.

Exception: Where the manufacturer is no longer in business, or the manufacturer or an entity acceptable to such manufacturer is unable to provide the anemometer, the anemometer may be approved by the department.

*Section 3319.13.1 was added by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*3319.13.2 Option 2: Anemometer at the site

An anemometer located at a high point of the site approximate to the height and location of the crane or derrick boom/jib, freely exposed to the wind, and calibrated in accordance with ASTM D5096-02. The anemometer must measure a 3-second gust wind. A real time display of the anemometer must be available to the hoisting machine operator at the operator's station, or a person designated by the hoisting machine operator must be provided to monitor the display and alert the hoisting machine operator when measurements near, meet, or exceed the thresholds specified in the approved wind action plan. Such anemometer is to be considered an operational aid and must be checked prior to each shift as required by department rules.

*Section 3319.13.2 was added by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*3319.13.3 Option 3: Nearest weather station

The most recent gust wind speed reported at the nearest National Weather Service weather station. The equipment user must establish a system to ensure the hoisting machine operator is notified when reported wind gusts near, meet, or exceed the thresholds specified in the approved wind action plan. An acceptable system may include engaging a metrological service to provide a text or similar alert to a person designated by the equipment user when wind thresholds are neared, met, or exceeded, and have such designated person notify the hoisting machine operator.

*Section 3319.13.3 was added by Local Law 13 of 2018. This law has an effective date of April 30, 2018.

*3319.13 Age limitations for cranes

Only cranes having an age of less than 25 years from the manufacture date may be used in New York City. Notwithstanding the provisions of Section 3319.5, the certificate of operation for a crane with an age greater than 25 years from the manufacture date shall be deemed to have expired.

Exceptions:
  1. A crane with an age of 25 years or greater from the manufacture date that is (i) in use on a project on January 1, 2019 or (ii) not in use on January 1, 2019, but for which an application for a certificate of on-site inspection has been approved as of January 1, 2019, may continue to be used until completion of the project for which it is being used or the project for which such certificate of onsite inspection was issued.
  2. Where a crane with an age of less than 25 years from the manufacture date at the time the department approved the application for a certificate of on-site inspection is being used on a project and will each an age of 25 years or greater from the manufacture date during such project, such crane may be used for the duration of that project or until it reaches 28 years of age, whichever occurs earlier.
  3. The commissioner may approve the use of a crane with an age of 25 years or greater from the manufacture date for up to a maximum of five years, not to exceed 30 years from the manufacture date, when records as required by rule of the department are deemed sufficient by the commissioner to establish that such crane meets the manufacturer's standards for use.
  4. This section shall not apply to equipment used for pile driving or clamshell work.
*Section 3319.13 was added by Local Law 3 of 2018. This law has an effective date of January 1, 2019. The mis-numbering will be corrected in future legislation.
Share URL

Copy and paste the link below into emails, chats or browsers.

Copy

You can also copy or bookmark the link from your browser's address bar.

Related Code Sections


Section 3319 Safeguards During Construction or Demolition, Cranes and Derricks
No owner or other person shall authorize or permit the operation of any crane or derrick without ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks
Section 3319 Safeguards During Construction or Demolition, Cranes and Derricks
construction, installation, inspection, maintenance and use of cranes and derricks shall be in conformance with the requirements of this section, Section ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks
§28-112.6.2 Administration, Withdrawal of Cranes and Derricks Applications
If the applicant withdraws his or her application for a certificate of approval for a power-operated crane, derrick or cableway, such applicant may ...
NYC General Admin. Provisions 2014 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.2 Withdrawal of Cranes and Derricks Applications
§28-112.6.2 Administration, Withdrawal of Cranes and Derricks Applications
If the applicant withdraws his or her application for a certificate of approval for a power-operated crane, derrick or cableway, such applicant may ...
NYC General Admin. Provisions 2008 > 1 Administration > 112 Fees > §28-112.6 Refunds and Rebates > §28-112.6.2 Withdrawal of Cranes and Derricks Applications
3308.1.6 Safeguards During Construction or Demolition, Designated Crane and Derrick Lifting Areas
Required horizontal safety netting may be omitted in designated crane and derrick lifting areas so long as such lifting area is as indicated ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3308 Safety Netting > 3308.1 Safety Netting During Construction or Demolition Operations > 3308.1.6 Designated Crane and Derrick Lifting Areas
About UpCodes

UpCodes provides an intuitive resource to navigate building regulations.

Codes are organized by jurisdiction to help you understand which regulations apply to your project.


Find Your Codes
COMPANY INFO About Free Law Contact Careers Terms Privacy Press Kit
CATEGORY General New York City New York State California Codes Building Codes Online
PREMIUM Features Pricing Sign Up Log In
CODES IBC 2015 IRC 2015 IPC 2015 California Building Code 2016 Popular Sections

FOLLOW US