[F] 909.13 Control Air Tubing
JUMP TO FULL CODE CHAPTER
Control air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections and shall be adequately supported and protected from damage. Tubing passing through concrete or masonry shall be sleeved and protected from abrasion and electrolytic action.
Control-air tubing shall be harddrawn copper, Type L, ACR in accordance with ASTM B42, ASTM B43, ASTM B68, ASTM B88, ASTM B251 and ASTM B280. Fittings shall be wrought copper or brass, solder type in accordance with ASME B16.18 or ASME B16.22. Changes in direction shall be made with appropriate tool bends. Brass compression-type fittings shall be used at final connection to devices; other joints shall be brazed using a BCuP-5 brazing alloy with solidus above 1,100°F (593°C) and liquids below 1,500°F (816°C). Brazing flux shall be used on copper-to-brass joints only.
Exception:
Nonmetallic tubing used within control panels and at the final connection to devices provided all of the following conditions are met:
- Tubing shall comply with the requirements of Section 602.2.1.3 of the International Mechanical Code.
- Tubing and connected devices shall be completely enclosed within a galvanized or paint-grade steel enclosure having a minimum thickness of 0.0296 inch (0.7534 mm) (No. 22 gage). Entry to the enclosure shall be by copper tubing with a protective grommet of neoprene or Teflon or by suitable brass compression to male barbed adapter.
- Tubing shall be identified by appropriately documented coding.
- Tubing shall be neatly tied and supported within the enclosure.Tubing bridging cabinets and doors or moveable devices shall be of sufficient length to avoid tension and excessive stress. Tubing shall be protected against abrasion. Tubing serving devices on doors shall be fastened along hinges.
Control tubing serving other than smoke control functions shall be isolated by automatic isolation valves or shall be an independent system.
Control air tubing shall be tested at three times the operating pressure for not less than 30 minutes without any noticeable loss in gauge pressure prior to final connection to devices.
Related Code Sections
513.13 Exhaust Systems, Control-Air Tubing
Control-air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections ...
2015 Washington State Mechanical Code > 5 Exhaust Systems > 513 Smoke Control Systems > 513.13 Control-Air Tubing
513.13 Exhaust Systems, Control-Air Tubing
Control-air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections ...
2018 Washington State Mechanical Code > 5 Exhaust Systems > 513 Smoke Control Systems > 513.13 Control-Air Tubing
909.13 Fire Protection Systems, Control Air Tubing
Control air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections ...
2015 Washington State Building Code > 9 Fire Protection Systems > 909 Smoke Control Systems > 909.13 Control Air Tubing
909.13 Fire Protection Systems, Control Air Tubing
Control air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections ...
2015 Washington State Fire Code > 9 Fire Protection Systems > 909 Smoke Control Systems > 909.13 Control Air Tubing
909.13 Fire Protection and Life Safety Systems, Control Air Tubing
Control air tubing shall be of sufficient size to meet the required response times. Tubing shall be flushed clean and dry prior to final connections ...
2018 Washington State Building Code > 9 Fire Protection and Life Safety Systems > 909 Smoke Control Systems > 909.13 Control Air Tubing