// CODE SNIPPET
G311.3 Connections for Temporary External Boilers and Chillers
JUMP TO FULL CODE CHAPTER
Buildings whose main use or dominant occupancy is Group I-2 hospital that are located in an area of special flood hazard or shaded X-Zone shall be provided with connections for temporary external boilers and chillers in accordance with Section G304.5.2 by January 1, 2033, and a report detailing compliance with such requirements shall be filed with the department in accordance with Section G311.3.2 by such date.
Where the area of special flood hazard or shaded X-Zone is modified on or after the effective date of this section, any building whose main use or dominant occupancy is Group I-2 hospital and that is newly identified as being within such modified area of special flood hazard or shaded X-Zone shall comply with the retroactive requirements of Section G311.3 no later than 20 years following the adoption of such modification. The owner of such building shall file with the department a report detailing compliance with such requirements in accordance with section G311.3.2 no later than 20 years following the adoption of such modification.
The owner of a building required to comply with the provisions of Section G311.3 shall file with the department, by January 1, 2033, a report prepared by a registered design professional (i) certifying that the requirements of Section G311.3 have been satisfied and detailing how much requirements were satisfied or (ii) certifying that any boiler and chiller plants that serve the spaces specified in Item 2 of Section G304.5.2 are located at or above the design flood elevation specified in Table 7-1 of ASCE 24.
The department may promulgate rules establishing filing fees for the review and examination of such reports.
Related Code Sections
G311.3 Flood-Resistant Construction, Connections for Temporary External Boilers and Chillers
be provided with connections for temporary external boilers and chillers in accordance with Section G304.5.2 by January 1, 2033, and a report detailing ...
NYC Building Code 2014 > G Flood-Resistant Construction > G311 Retroactive Requirements > G311.3 Connections for Temporary External Boilers and Chillers
§28-315.8.3 Maintenance of Buildings, Connections for Temporary External Boilers and Chillers
, as such terms are defined in appendix G of the New York city building code, the provision of connections for temporary external boilers and chillers ...
NYC General Admin. Provisions 2014 > 3 Maintenance of Buildings > 315 Retroactive Requirements > §28-315.8 Resiliency > §28-315.8.3 Connections for Temporary External Boilers and Chillers
G304.5.2 Flood-Resistant Construction, Group I-2 Hospitals
hours.
Flood protection for temporary external generator, boiler and chiller connections. Electrical connections installed in accordance ...
NYC Building Code 2014 > G Flood-Resistant Construction > G304 Post-Firm Construction and Substantial Improvements > G304.5 Additional Construction Standards With Respect to Connections for Temporary External Generators, Boilers and Chillers > G304.5.2 Group I-2 Hospitals
§28-104.7.15 Administration, Identification of Certain Hospitals as Exempt From Temporary External Boiler or Chiller Connection Requirements
external boilers and chillers pursuant to Item 2 of section G304.5.2 is inapplicable as a result of such building having its boiler and chiller plants ...
NYC General Admin. Provisions 2014 > 1 Administration > 104 Construction Documents > §28-104.7 Submittal of Construction Documents > §28-104.7.15 Identification of Certain Hospitals as Exempt From Temporary External Boiler or Chiller Connection Requirements
G304.5.1 Flood-Resistant Construction, Group I-1 and Adult Homes, Enriched Housing, Community Residences and Intermediate Care Facilities
for temporary external generators. Electrical connections shall be provided allowing for the connection of temporary external generators capable of providing ...
NYC Building Code 2014 > G Flood-Resistant Construction > G304 Post-Firm Construction and Substantial Improvements > G304.5 Additional Construction Standards With Respect to Connections for Temporary External Generators, Boilers and Chillers > G304.5.1 Group I-1 and Adult Homes, Enriched Housing, Community Residences and Intermediate Care Facilities