// CODE SNIPPET
1926.702(e) Concrete Pumping Systems
JUMP TO FULL CODE CHAPTER
Concrete pumping systems using discharge pipes shall be provided with pipe supports designed for 100 percent overload.
Compressed air hoses used on concrete pumping system shall be provided with positive fail-safe joint connectors to prevent separation of sections when pressurized.
Related Code Sections
1926.702(e) Concrete and Masonry Construction, Concrete Pumping Systems
Concrete pumping systems using discharge pipes shall be provided with pipe supports designed for 100 percent overload ...
OSHA 1926 Construction > Q Concrete and Masonry Construction > 1926.702 Requirements for Equipment and Tools > 1926.702(e) Concrete Pumping Systems
1926.1400(c)(1) Cranes & Derricks in Construction,
/adaptations include, but are not limited to, power shovels, excavators and concrete pumps ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1400 Scope > 1926.1400(c) Exclusions > 1926.1400(c)(1)
1926.152(k)(2) Fire Protection and Prevention, Tanks and Pumps
Tanks, and pumps not integral with the dispensing unit, shall be on shore or on a pier of the solid fill type, except as provided in paragraphs (k)(2 ...
OSHA 1926 Construction > F Fire Protection and Prevention > 1926.152 Flammable Liquids > 1926.152(k) Marine Service Stations > 1926.152(k)(2) Tanks and Pumps
1926.501(b)(12) Fall Protection, Precast Concrete Erection
Each employee engaged in the erection of precast concrete members (including, but not limited to the erection of wall panels, columns, beams ...
OSHA 1926 Construction > M Fall Protection > 1926.501 Duty to Have Fall Protection > 1926.501(b) > 1926.501(b)(12) Precast Concrete Erection
1926.1201(a) Confined Spaces in Construction,
spaces may occur include, but are not limited to, the following: Bins; boilers; pits (such as elevator, escalator, pump, valve or other equipment ...