E303 Concrete Floors in Contact With Soil Gas.
Mix design for all concrete used in the construction of slab-on-grade floors shall specify a maximum design slump not to exceed 4 inches (102 mm). On-site slumps shall not exceed 5 inches (127 mm) provided that the total water added to the mix, including plant, transit, and site added water, does not exceed the total following parameters:
Concrete floors shall be cured by one of the means described below and shall not be subjected to loading until the architect or engineer has determined the slab to be structurally adequate for the loads imposed.
- Concrete floor slabs shall be cured by covering the entire slab surface for a period of seven days with clean, ponded water.
- Concrete floor slabs shall be cured by covering the entire slab surface for a period of seven days with a continuous mist or spray of clean, potable water.
- Concrete floor slabs shall be cured by covering the entire slab surface for a period of seven days with an impermeable sheet material conforming to ASTM C171.
- Concrete floor slabs shall be cured by covering the entire slab surface with a liquid membrane-forming compound that conforms with ASTM C309. Curing compounds shall be compatible with materials specified in Section E303.3.1.
Sealants shall be selected and installed in compliance with ASTM C920, Standard Specification for Elastomeric Joint Sealants, and ASTM C 1193, Standard Guide for Use of Joint Sealants.
- Sealant materials shall be compatible with the materials they join, including curing compounds and admixtures, and with materials that will be applied over them, including floor finishing materials.
- Field-molded sealants shall be installed in sealant reservoirs proportioned, cleaned of laitance and prepared in accordance with the manufacturer's recommendations. For elastomeric sealants, this generally requires the installation of a bond breaker or backer rod.
- When the installed sealant is not protected by a finished floor or other protective surface, it shall be suitable to withstand the traffic to which it will be exposed.
- Waterstops shall be preformed from polyvinyl chloride or other noncorrosive material and shall be selected and installed in compliance with ACI 504R
All joints between sections of concrete floor slabs, between the floor slab and a wall or other vertical surface, or between a section of floor and another object that passes through the slab, shall be sealed to prevent soil gas entry in accordance with the provisions of this section. Joint design depends upon the amount and type of movement that the joint must withstand. Ideally, sealing should occur as late in the construction process as possible. No portion of any joint shall be covered or rendered inaccessible unless the seal has first been inspected and approved by the building official. All such joints shall be sealed prior to the structure being certified for occupancy.
- Butt joints. All nonbonded butt joints shall be sealed to prevent radon entry using an elastomeric sealant or a waterstop specified above. The sealant reservoir shall be sufficiently large to prevent failure of the sealant or waterstop, but in no case shall the sealant reservoir be less than 1/4 inch by 1/4 inch (6.4 mm by 6.4 mm) in cross section
- Lap joints. All nonbonded lap joints shall be sealed with either a field-molded or preformed elastomeric sealant or with a flexible waterstop as specified above. The lap joint shall be sufficiently large to prevent failure of the sealant or waterstop, but in no case shall the sealant reservoir be less than 1/2 inch by 1/2 inch (12.7 mm by 12.7 mm) in cross section.
- Isolation joints. All nonbonded isolation joints shall be sealed with either a field-molded or preformed elastomeric sealant or with a flexible waterstop as specified above. Isolation joints shall be sufficiently large to prevent failure of the sealant or waterstop, but in no case shall the sealant reservoir be less than 1/2 inch by 1/2 inch (12.7 mm by 12.7 mm) in cross section.
- Control or contraction joints. May be used to limit unplanned cracking of floor slabs. In locations where continued movement of the slab portions can be reasonably expected, flexible sealants must be installed in reservoirs complying with the requirements of above section on butt joints, or a flexible waterstop must be used.
- Construction joints. All bonded construction joints shall be sealed to prevent radon entry using either a rigid or an elastomeric sealant or a waterstop as specified above. Where movement of the joint is not prevented by continuous reinforcing and tie bars, flexible sealants must be installed in reservoirs complying with the requirements of above section on lap joints, or a flexible waterstop must be used.
All cracks in concrete slabs supported on soil or spanning over exposed soil, that are used as floors for conditioned space or enclosed spaces adjacent to or connected to conditioned spaces, shall be sealed against radon entry in accordance with the provisions of this section and Section E303.3.1. Ideally, sealing should occur as late in the construction process as possible.
- Cracks greater than 1/4 inch (6.4 mm) wide; all cracks that exhibit vertical displacement; all cracks that connect weakened zones in the slab such as vertical penetrations or re-entrant corners; and, all cracks that cross changes in materials or planes in the structure, shall be sealed with a flexible field-molded elastomeric sealant installed in accordance with above section on isolation joints.
- Cracks greater than 1/16 inch (1.6 mm) in width, that do not meet any of the conditions described in Item 1 above, shall be enlarged to contain a sealant reservoir not less than 1/2 inch by 1/4 inch (12.7 mm by 6.4 mm) in cross-section along the entire length of the crack; and shall be sealed with a flexible, field-molded elastomeric sealant installed in accordance with above section on butt joints.
- Cracks less than 1/16 inch (1.6 mm) in width, that do not meet any of the conditions described in Item 1 above, may be left unsealed.
All objects that pass through the slab shall be sealed gas tight. A sealant reservoir, appropriately dimensioned to accommodate any differential movement between the object and the concrete, shall be formed continuously around the object, and the joint shall be sealed with a field molded elastomeric sealant as prescribed for isolation joints and in accordance with the provisions of Section E303.3.1. Where pipes or other penetrations are separated from the concrete by flexible sleeves, the sleeve shall be removed to provide bonding of the sealant to the object. Where stakes are used to support plumbing, electrical conduits or other objects that will penetrate the slab, the stakes shall be solid, non-porous and resistant to decay, corrosion and rust. Special care must be taken to avoid honeycombing between multiple or ganged penetrations.
- Large utility service openings through the slab shall be sealed gas-tight. For slab-on-grade construction, this can be accomplished by fully covering the exposed soil with a vapor-retarder membrane, covered to a minimum depth of 1 inch with an elastomeric sealant. Alternatively, the opening may be closed with an expansive concrete or hydraulic cement to within 1/2 inch (12.7 mm) of the top of the slab, and the remaining 1/2 inch (12.7 mm) filled with an elastomeric sealant. When the opening connects to a crawlspace, the opening shall be closed with sheet metal or other rigid impermeable materials and sealed with an elastomeric sealant compatible with the materials and conditions.
- For openings made through existing slabs, they must be sealed to meet the appropriate provisions of this section. If the opening is partially repaired with concrete, any resulting crack shall be sealed in accordance with the Section E303.3.3.
- Any sump located in a habitable portion of a building and connecting to the soil, either directly or through drainage piping, shall be fined with a gasketed lid. The lid shall be attached so as to provide a gas-tight seal between the sump and the access space above.