3307.6.5.5 Cleaning
Related Code Sections
3307.6.5.5 Safeguards During Construction or Demolition, Cleaning
The decks of sidewalk sheds shall be broom swept and cleaned of material daily while active work is occurring at the site ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3307 Protection of Pedestrians > 3307.6 Sidewalk Sheds > 3307.6.5 Installation, Adjustment, Maintenance, Repair, Use, Inspection, and Removal of Sidewalk Sheds > 3307.6.5.5 Cleaning
3307.6.5.5 Safeguards During Construction or Demolition, Cleaning
The decks of sidewalk sheds shall be broom swept and cleaned of material daily while active work is occurring at the site ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3307 Protection of Pedestrians > 3307.6 Sidewalk Sheds > 3307.6.5 Installation, Adjustment, Maintenance, Repair, Use, Inspection, and Removal of Sidewalk Sheds > 3307.6.5.5 Cleaning
3308.6.2.11 Safeguards During Construction or Demolition, Cleaning
Horizontal netting shall be cleaned, at least daily, to remove any items that fall into
the nets." ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3308 Unenclosed Perimeter Protection > 3308.6 Horizontal Safety Netting Systems > 3308.6.2 Horizontal Safety Netting Systems Requirements > 3308.6.2.11 Cleaning
3308.6.2.11 Safeguards During Construction or Demolition, Cleaning
Horizontal netting shall be cleaned, at least daily, to remove any items that fall into the nets." ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3308 Protection of Unenclosed Perimeters > 3308.6 Horizontal Safety Netting Systems > 3308.6.2 Horizontal Safety Netting Systems Requirements > 3308.6.2.11 Cleaning
507.1.4 Exhaust Systems, Cleaning
A hood shall be designed to facilitate thorough cleaning of the entire hood ...
NYC Mechanical Code 2022 > 5 Exhaust Systems > 507 Commercial Kitchen Hoods > 507.1 General > 507.1.4 Cleaning