// CODE SNIPPET
§28-101.4.5.1 Changes in Scope of Work
JUMP TO FULL CODE CHAPTER
In cases where changes in the scope of work during the course of construction would result in increasing the floor surface area at the completion of construction by more than 110 percent over the amount of existing floor surface area as determined pursuant to section 28-101.4.5, such entire building shall be made to comply with the provisions of this code as if hereafter erected and such work shall be refiled as a new building application in accordance with the provisions of section 28-105.2.
Exception: Work to the extent necessary to relieve an emergency condition may be performed prior to amending plans or obtaining a new permit pursuant to sections 28-105.4.1 and 28-105.12.2.
Related Code Sections
§28-101.4.5.1 Administration, Changes in Scope of Work
In cases where changes in the scope of work during the course of construction would result in increasing the floor surface area ...
NYC General Admin. Provisions 2014 > 1 Administration > 101 General > §28-101.4 Effective Date > §28-101.4.5 Work That Increases Existing Floor Surface Area of a Prior Code Building by More Than 110 Percent > §28-101.4.5.1 Changes in Scope of Work
§28-101.4.5.1 Administration, Changes in Scope of Work
In cases where changes in the scope of work during the course of construction would result in increasing the floor surface area ...
NYC General Admin. Provisions 2022 > 1 Administration > 101 General > §28-101.4 Effective Date > §28-101.4.5 Work That Increases Existing Floor Surface Area of a Prior Code Building by More Than 110 Percent > §28-101.4.5.1 Changes in Scope of Work
*3301.13 Safeguards During Construction or Demolition, Scope
as defined by this code, and any and all documents that set forth the
location and entire nature and extent of the work proposed with sufficient clarity ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3301 General > *3301.13 Scope
*3301.13 Safeguards During Construction or Demolition, Scope
as defined by this code, and any and all documents that set forth the location and entire nature and extent of the work proposed with sufficient clarity ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3301 General > *3301.13 Scope
1103.2.2 Accessibility, Employee Work Areas
the ground or finished floor where the change in elevation is critical to the work operation shall be exempt from all requirements ...
NYC Building Code 2022 > 11 Accessibility > 1103 Scoping Requirements > 1103.2 General Exceptions > 1103.2.2 Employee Work Areas