611.4 Building Envelope Systems Commissioning and Completion Requirements
JUMP TO FULL CODE CHAPTER
Prior to issuance of a certificate of occupancy, the registered design professional shall provide evidence of building thermal envelope systems commissioning and completion to the building owner in accordance with the International Energy Conservation Code and the provisions of this section.
Construction documents shall specify the provisions for commissioning and completion requirements in accordance with this section and are permitted to refer to specifications for further requirements. Copies of all documentation shall be given to the building owner and made available to the code official upon request in accordance with Sections 611.4.1 and 611.4.2.
Construction and owner education documents shall indicate the location, nature and extent of the work proposed and show the functional requirements and operation of all building thermal envelope systems demonstrating conformance to the provisions of this code, relevant laws, ordinances, rules and regulations, as approved by the code official.
The approved agency conducting commissioning shall verify that building thermal envelope systems have been installed in accordance with the approved construction documents. Any discrepancies shall be reviewed for compliance with requirements of the International Energy Conservation Code and this code.
Related Code Sections
611.4 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Building Envelope Systems Commissioning and Completion Requirements
the functional requirements and operation of all building thermal envelope systems demonstrating conformance to the provisions of this code, relevant laws ...
Green Construction Code 2012 of Maryland > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.4 Building Envelope Systems Commissioning and Completion Requirements
Section 903 Commissioning, Operation and Maintenance, Commissioning
or test reports During commissioning Annually 603, 610.5 Mechanical systems completion — all buildings a. Air system balancing — provide ...
Green Construction Code 2012 of Maryland > 9 Commissioning, Operation and Maintenance > 903 Commissioning
611.1.5.4 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Final Commissioning Report
A complete report of test procedures and results identified as "Final Commissioning Report" shall be completed and provided to the building owner ...
Green Construction Code 2012 of Maryland > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.1 Mechanical Systems Commissioning and Completion Requirements > 611.1.5 Completion Requirements > 611.1.5.4 Final Commissioning Report
611.1.4 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Preliminary Commissioning Report
A preliminary report of commissioning test procedures and results shall be completed and certified by the registered design professional ...
Green Construction Code 2012 of Maryland > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.1 Mechanical Systems Commissioning and Completion Requirements > 611.1.4 Preliminary Commissioning Report
Section C408 [CE] Commercial Energy Efficiency, System Commissioning
This section covers the commissioning of the building mechanical systems in Section C403 and electrical power and lighting systems in Section C405 ...
Energy Conservation Code 2015 of Maryland > 4 [CE] Commercial Energy Efficiency > C408 System Commissioning