• Codes
  • Features

    Features Overview

    Go to features
    Reference

    Reference.

    A reliable and up-to-date source of codes.
    Research

    Research.

    Rapidly and efficiently calculate project parameters.
    Collaboration

    Collaboration.

    Get everyone on the same page and streamline code research.
    Workflows
    Architects General Contractor Building Official & Plans Examiner Inspectors Owner Subcontractors Code Consultants
  • Pricing
  • Login
  • Sign Up
Sign Up
Login
  • Code Library
  • Features
  • Pricing
  • About
  • Careers
  • Help
  • Contact
  • Terms
  • Privacy
Sign Up
Upgrade to Premium
Code calculators: Code Calculators automatically generates a detailed list of requirements.
REFERENCE
Amendment Styling
Industry-leading search
Suggested code sections
Code diagrams
RESEARCH
Code calculators
Filter by topic
Code compare
Code sheet exports
COLLABORATION
Team projects
Bookmarks
Comments
START 2 WEEK FREE TRIAL
Have an account? Sign in
// CODE SNIPPET

611.10 Building Envelope Systems Commissioning

Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion > 611.10 Building Envelope Systems Commissioning
JUMP TO FULL CODE CHAPTER
Building thermal envelope, dynamic glazing and shading device systems shall be commissioned and completion documentation shall be provided to the building owner in accordance with the International Energy Conservation Code and the provisions of this section.

611.10.1 Preconstruction Documentation, Building Thermal Envelope

Construction and owner education documents shall indicate the location, nature and extent of the work proposed and show the functional requirements and operation of the building thermal envelope, dynamic glazing and shading device systems demonstrating conformance to the provisions of this code.

611.10.2 Continuous Air Barrier Commissioning

Prior to final inspection, the registered design professional or approved agency shall provide evidence of continuous air barrier commissioning that shall include:
  1. Clear identification of the continuous air barrier components specified for the project and identified on approved construction documents.
  2. Review of planned construction details to ensure continuity of the air barrier over the entire building thermal envelope.
  3. A field inspection checklist clearly showing the requirements necessary for proper installation of the continuous air barrier.
  4. Witnessing and reporting on any continuous air barrier testing specified by the owner.
  5. Periodic field inspections over the course of project construction to ensure compliance with the continuous air barrier requirements including, but not limited to, proper material handling and storage, use of approved materials and approved substitutes, proper material and surface preparation, air barrier continuity at all building thermal envelope penetrations and other requirements as necessary for achieving the performance objective of the continuous air barrier.
  6. A final commissioning report provided to the building owner and code official demonstrating compliance with the continuous air barrier requirements.

611.10.3 Continuous Air Barrier Commissioning Report

A final commissioning report shall be delivered to the building owner, and shall include:
  1. A field inspection checklist showing the requirements necessary for proper installation of the continuous air barrier.
  2. The results of any building air leakage testing.
  3. Reports from field inspections during project construction showing compliance with continuous air barrier requirements including, but not limited to, proper material handling and storage, use of approved materials and approved substitutes, proper material and surface preparation and air barrier continuity at building thermal envelope penetrations.

Related Code Sections


611.10 Energy Conservation, Efficiency and Co2e Emission Reduction, Building Envelope Systems Commissioning
Building thermal envelope, dynamic glazing and shading device systems shall be commissioned and completion documentation shall be provided ...
Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion > 611.10 Building Envelope Systems Commissioning
611.4 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Building Envelope Systems Commissioning and Completion Requirements
The approved agency conducting commissioning shall verify that building thermal envelope systems have been installed ...
Green Construction Code 2012 > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.4 Building Envelope Systems Commissioning and Completion Requirements
Section 611 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Energy Systems Commissioning and Completion
of building thermal envelope systems commissioning and completion to the building owner in accordance with the International Energy Conservation Code ...
Green Construction Code 2012 > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion
Section 611 Energy Conservation, Efficiency and Co2e Emission Reduction, Energy Systems Commissioning and Completion
to the code official that installation and commissioning of systems have been completed, and that commissioned building systems have been installed ...
Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion
Help Contact Us Privacy Terms
Search
Search
Don't miss relevant code. Quickly locate sections across your jurisdiction.
Code Compare
Code Compare
Highlight differences between any two building codes.
Shared projects
Shared projects
Projects provide a dedicated space to collaborate on code research.
Code sheet exports
Code sheet exports
Generate a code sheet that integrates with your drawing set.
Code Calculators
Code Calculators
Code calculators automatically generate a detailed list of requirements.
Code diagrams
Code diagrams
Unpack the code through illustrations and descriptions.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
TRY FREE FOR TWO WEEKS VISIT PRICING
UpCodes Premium
Leverage the full code compliance platform.
START 2 WEEK FREE TRIAL LEARN MORE