// CODE SNIPPET
703.1 Building Drain Pipe Near the Water Service
JUMP TO FULL CODE CHAPTER
Where the building drain is installed underground and within 5 feet (1524 mm) of the water service, as provided for in Section 603.2, the building drain pipe shall conform to one of the standards for, cast-iron pipe, copper or copper-alloy tubing, or ductile iron listed in Table 702.3.
Related Code Sections
703.1 Sanitary Drainage, Building Drain Pipe Near the Water Service
Where the building drain is installed underground and within 5 feet (1524 mm) of the water service, as provided for in Section 603.2, the building ...
NYC Plumbing Code 2022 > 7 Sanitary Drainage > 703 Building Drain > 703.1 Building Drain Pipe Near the Water Service
Reference Standard 16 Plumbing and Gas Piping [PDF] (page 28)
horizontally, and shall be separated by compacted earth. The water service may be placed in the same trench with the building sewer and building drain ...
Section 603 Water Supply and Distribution, Water Service
). Underground water service pipe and the building sewer or the building drain shall be separated by not less than 5 feet (1524 mm) of undisturbed ...
Article 15 Plumbing and Gas Piping [PDF] (page 19)
president and the rules of the board. (14.9.7). §C26-1287.0 House Drains for Rear Buildings.-When a structure stands in the rear of another structure ...
1301.9.9 Nonpotable Water Systems, Draining of Tanks
The tank drain pipe shall be indirectly connected to the appropriate building drainage system and discharge as required for overflow pipes and shall ...
NYC Plumbing Code 2022 > 13 Nonpotable Water Systems > 1301 General > 1301.9 Nonpotable Water Storage Tanks > 1301.9.9 Draining of Tanks