• Codes
  • Features

    Features Overview

    Go to features
    Reference

    Reference.

    A reliable and up-to-date source of codes.
    Research

    Research.

    Rapidly and efficiently calculate project parameters.
    Collaboration

    Collaboration.

    Get everyone on the same page and streamline code research.
    Workflows
    Architects General Contractor Building Official & Plans Examiner Inspectors Owner Subcontractors Code Consultants
  • Pricing
  • Login
  • Sign Up
Sign Up
Login
  • Code Library
  • Features
  • Pricing
  • About
  • Careers
  • Help
  • Contact
  • Terms
  • Privacy
Sign Up
Upgrade to Premium
Code calculators: Code Calculators automatically generates a detailed list of requirements.
REFERENCE
Amendment Styling
Industry-leading search
Suggested code sections
Code diagrams
RESEARCH
Code calculators
Filter by topic
Code compare
Code sheet exports
COLLABORATION
Team projects
Bookmarks
Comments
START 2 WEEK FREE TRIAL
Have an account? Sign in
// CODE SNIPPET

Subpart P App B - Sloping and Benching

OSHA 1926 Construction > P Excavations > P App B - Sloping and Benching
JUMP TO FULL CODE CHAPTER
  1. Scope and application. This appendix contains specifications for sloping and benching when used as methods of protecting employees working in excavations from cave-ins. The requirements of this appendix apply when the design of sloping and benching protective systems is to be performed in accordance with the requirements set forth in § 1926.652(b)(2).
  2. Definitions.

    Actual slope means the slope to which an excavation face is excavated.

    Distress means that the soil is in a condition where a cave-in is imminent or is likely to occur. Distress is evidenced by such phenomena as the development of fissures in the face of or adjacent to an open excavation; the subsidence of the edge of an excavation; the slumping of material from the face or the bulging or heaving of material from the bottom of an excavation; the spalling of material from the face of an excavation; and ravelling, i.e., small amounts of material such as pebbles or little clumps of material suddenly separating from the face of an excavation and trickling or rolling down into the excavation.

    Maximum allowable slope means the steepest incline of an excavation face that is acceptable for the most favorable site conditions as protection against cave-ins, and is expressed as the ratio of horizontal distance to vertical rise (H:V).

    Short term exposure means a period of time less than or equal to 24 hours that an excavation is open.
  3. Requirements -

    1. Soil classification. Soil and rock deposits shall be classified in accordance with appendix A to subpart P of part 1926.
    2. Maximum allowable slope. The maximum allowable slope for a soil or rock deposit shall be determined from Table B-1 of this appendix.
    3. Actual slope.

      1. The actual slope shall not be steeper than the maximum allowable slope.
      2. The actual slope shall be less steep than the maximum allowable slope, when there are signs of distress. If that situation occurs, the slope shall be cut back to an actual slope which is at least 1/2 horizontal to one vertical ( 1/2 H:1V) less steep than the maximum allowable slope.
      3. When surcharge loads from stored material or equipment, operating equipment, or traffic are present, a competent person shall determine the degree to which the actual slope must be reduced below the maximum allowable slope, and shall assure that such reduction is achieved. Surcharge loads from adjacent structures shall be evaluated in accordance with § 1926.651(i).
    4. Configurations. Configurations of sloping and benching systems shall be in accordance with Figure B-1.

      TABLE B-1
      MAXIMUM ALLOWABLE SLOPES
      SOIL OR ROCK TYPE MAXIMUM ALLOWABLE SLOPES (H:V)(1) FOR EXCAVATIONS LESS THAN 20 FEET DEEP(3)
      STABLE ROCK VERTICAL (90°)
      TYPE A (2) 3/4:1 (53°)
      TYPE B 1:1 (45°)
      TYPE C 1 1/2:1 (34°)
      Footnote(1) Numbers shown in parentheses next to maximum allowable slopes are angles expressed in degrees from the horizontal. Angles have been rounded off.

      Footnote(2) A short-term maximum allowable slope of 1/2H:1V (63°) is allowed in excavations in Type A soil that are 12 feet (3.67 m) or less in depth. Short-term maximum allowable slopes for excavations greater than 12 feet (3.67 m) in depth shall be 3/4H:1V (53°).

      Footnote(3) Sloping or benching for excavations greater than 20 feet deep shall be designed by a registered professional engineer.

Figure B-1

Slope Configurations
(All slopes stated below are in the horizontal to vertical ratio)

B-1.1 Excavations made in Type A soil

  1. All simple slope excavation 20 feet or less in depth shall have a maximum allowable slope of 3/4:1.

    Simple Slope - General


    Exception: Simple slope excavations which are open 24 hours or less (short term) and which are 12 feet or less in depth shall have a maximum allowable slope of 1/2:1.

    Simple Slope - Short Term
  2. All benched excavations 20 feet or less in depth shall have a maximum allowable slope of 3/4 to 1 and maximum bench dimensions as follows:

    Simple Bench

    Multiple Bench

  3. All excavations 8 feet or less in depth which have unsupported vertically sided lower portions shall have a maximum vertical side of 3 1/2 feet.

    Unsupported Vertically Sided Lower Portion - Maximum 8 Feet in Depth


    All excavations more than 8 feet but not more than 12 feet in depth which unsupported vertically sided lower portions shall have a maximum allowable slope of 1:1 and a maximum vertical side of 3 1/2 feet.

    Unsupported Vertically Sided Lower Portion - Maximum 12 Feet in Depth


    All excavations 20 feet or less in depth which have vertically sided lower portions that are supported or shielded shall have a maximum allowable slope of 1/4:1. The support or shield system must extend at least 18 inches above the top of the vertical side.

    Supported or Shielded Vertically Sided Lower Portion


  4. All other simple slope, compound slope, and vertically sided lower portion excavations shall be in accordance with the other options permitted under § 1926.652(b).

B-1.2 Excavations Made in Type B Soil
  1. All simple slope excavations 20 feet or less in depth shall have a maximum allowable slope of 1:1.

    Simple Slope


  2. All benched excavations 20 feet or less in depth shall have a maximum allowable slope of 1:1 and maximum bench dimensions as follows:

    Single Bench


    Multiple Bench

  3. All excavations 20 feet or less in depth which have vertically sided lower portions shall be shielded or supported to a height at least 18 inches above the top of the vertical side. All such excavations shall have a maximum allowable slope of 1:1.

    Vertically Sided Lower Portion


  4. All other sloped excavations shall be in accordance with the other options permitted in § 1926.652(b).

B-1.3 Excavations Made in Type C Soil

  1. All simple slope excavations 20 feet or less in depth shall have a maximum allowable slope of 1 1/2:1.

    Simple Slope


  2. All excavations 20 feet or less in depth which have vertically sided lower portions shall be shielded or supported to a height at least 18 inches above the top of the vertical side. All such excavations shall have a maximum allowable slope of 1 1/2:1.

    Vertical Sided Lower Portion


  3. All other sloped excavations shall be in accordance with the other options permitted in § 1926.652(b).

B-1.4 Excavations Made in Layered Soils
  1. All excavations 20 feet or less in depth made in layered soils shall have a maximum allowable slope for each layer as set forth below.

  2. All other sloped excavations shall be in accordance with the other options permitted in § 1926.652(b).

Related Code Sections


Subpart P Excavations, App B - Sloping and Benching
Configurations of sloping and benching systems shall be in accordance with Figure B-1. TABLE B-1 MAXIMUM ALLOWABLE SLOPES SOIL ...
OSHA 1926 Construction > P Excavations > P App B - Sloping and Benching
1926.652(b) Excavations, Design of Sloping and Benching Systems
The slopes and configurations of sloping and benching systems shall be selected and constructed by the employer or his designee and shall ...
OSHA 1926 Construction > P Excavations > 1926.652 Requirements for Protective Systems > 1926.652(b) Design of Sloping and Benching Systems
Subpart R Steel Erection, App B - [Reserved]
[66 FR 5273, Jan. 18, 2001; 71 FR 2885, Jan. 18, 2006 ...
OSHA 1926 Construction > R Steel Erection > R App B - [Reserved]
Subpart M Fall Protection, App A - Determining Roof Widths
Example B Sloped Rectangular Shaped Roofs Example C Irregularly Shaped Roofs With Rectangular Shaped Sections Such roofs ...
OSHA 1926 Construction > M Fall Protection > M App A - Determining Roof Widths
1926.652(b)(3) Excavations, Option (3)-Designs Using Other Tabulated Data
Designs of sloping or benching systems shall be selected from and be in accordance with tabulated data, such as tables and charts ...
OSHA 1926 Construction > P Excavations > 1926.652 Requirements for Protective Systems > 1926.652(b) Design of Sloping and Benching Systems > 1926.652(b)(3) Option (3)-Designs Using Other Tabulated Data
Help Contact Us Privacy Terms
Code sheet exports
Code sheet exports
Generate a code sheet that integrates with your drawing set.
Search
Search
Don't miss relevant code. Quickly locate sections across your jurisdiction.
Code Compare
Code Compare
Highlight differences between any two building codes.
Shared projects
Shared projects
Projects provide a dedicated space to collaborate on code research.
Code Calculators
Code Calculators
Code calculators automatically generate a detailed list of requirements.
Code diagrams
Code diagrams
Unpack the code through illustrations and descriptions.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
TRY FREE FOR TWO WEEKS VISIT PRICING
UpCodes Premium
Leverage the full code compliance platform.
START 2 WEEK FREE TRIAL LEARN MORE