Subpart R App A - Guidelines for Establishing the Components of a Site-Specific Erection Plan: Non-Mandatory Guidelines for Complying With § 1926.752(e)
JUMP TO FULL CODE CHAPTER
[66 FR 5273, Jan. 18, 2001]
- General. This appendix serves as a guideline to assist employers who elect to develop a site-specific erection plan in accordance with § 1926.752(e) with alternate means and methods to provide employee protection in accordance with § 1926.752(e), § 1926.753(c)(5), § 1926.757(a)(4) and § 1926.757(e)(4).
- Development of a site-specific erection plan. Pre-construction conference(s) and site inspection(s) are held between the erector and the controlling contractor, and others such as the project engineer and fabricator before the start of steel erection. The purpose of such conference(s) is to develop and review the site-specific erection plan that will meet the requirements of this section.
- Components of a site-specific erection plan. In developing a site-specific erection plan, a steel erector considers the following elements:
- The sequence of erection activity, developed in coordination with the controlling contractor, that includes the following:
- Material deliveries:
- Material staging and storage; and
- Coordination with other trades and construction activities.
- A description of the crane and derrick selection and placement procedures, including the following:
- Site preparation;
- Path for overhead loads; and
- Critical lifts, including rigging supplies and equipment.
- A description of steel erection activities and procedures, including the following:
- Stability considerations requiring temporary bracing and guying;
- Erection bridging terminus point;
- Anchor rod (anchor bolt) notifications regarding repair, replacement and modifications;
- Columns and beams (including joists and purlins);
- Connections;
- Decking; and
- Ornamental and miscellaneous iron.
- A description of the fall protection procedures that will be used to comply with § 1926.760.
- A description of the procedures that will be used to comply with § 1926.759.
- A description of the special procedures required for hazardous non-routine tasks.
- A certification for each employee who has received training for performing steel erection operations as required by § 1926.761.
- A list of the qualified and competent persons.
- A description of the procedures that will be utilized in the event of rescue or emergency response.
- The sequence of erection activity, developed in coordination with the controlling contractor, that includes the following:
- Other plan information. The plan:
- Includes the identification of the site and project; and
- Is signed and dated by the qualified person(s) responsible for its preparation and modification.
[66 FR 5273, Jan. 18, 2001]
Related Code Sections
Subpart R Steel Erection, App A - Guidelines for Establishing the Components of a Site-Specific Erection Plan: Non-Mandatory Guidelines for Complying With § 1926.752(e)
General . This appendix serves as a guideline to assist employers who elect to develop a site-specific erection plan in accordance ...
OSHA 1926 Construction > R Steel Erection > R App A - Guidelines for Establishing the Components of a Site-Specific Erection Plan: Non-Mandatory Guidelines for Complying With § 1926.752(e)
1926.752(e) Steel Erection, Site-Specific Erection Plan
at the work site. Guidelines for establishing a site-specific erection plan are contained in Appendix A to this subpart.
[66 FR 5267, Jan. 18 ...
OSHA 1926 Construction > R Steel Erection > 1926.752 Site Layout, Site-Specific Erection Plan and Construction Sequence > 1926.752(e) Site-Specific Erection Plan
Subpart R Steel Erection, App E - Training: Non-Mandatory Guidelines for Complying With 1926.761
The training requirements of § 1926.761 will be deemed to have been met if employees have completed a training course on steel erection, including ...
OSHA 1926 Construction > R Steel Erection > R App E - Training: Non-Mandatory Guidelines for Complying With 1926.761
1926.752(a)(1) Steel Erection,
the loads imposed during steel erection ...
OSHA 1926 Construction > R Steel Erection > 1926.752 Site Layout, Site-Specific Erection Plan and Construction Sequence > 1926.752(a) Approval to Begin Steel Erection > 1926.752(a)(1)
1926.752(a)(2) Steel Erection,
Any repairs, replacements and modifications to the anchor bolts were conducted in accordance with § 1926.755(b ...
OSHA 1926 Construction > R Steel Erection > 1926.752 Site Layout, Site-Specific Erection Plan and Construction Sequence > 1926.752(a) Approval to Begin Steel Erection > 1926.752(a)(2)