// CODE SNIPPET
1926.1441(d)(2) Anti Two-Blocking
JUMP TO FULL CODE CHAPTER
The employer must ensure that equipment covered by this section manufactured more than one year after November 8, 2010 have either an anti two-block device that meets the requirements of § 1926.1416(d)(3), or is designed so that, in the event of a two-block situation, no damage or load failure will occur (for example, by using a power unit that stalls in response to a two-block situation).
Related Code Sections
1926.1441(d)(2) Cranes & Derricks in Construction, Anti Two-Blocking
The employer must ensure that equipment covered by this section manufactured more than one year after November 8, 2010 have either an anti two-block ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1441 Equipment With a Rated Hoisting/Lifting Capacity of 2,000 Pounds or Less > 1926.1441(d) Safety Devices and Operational Aids > 1926.1441(d)(2) Anti Two-Blocking
1926.1431(d)(5)(v) Cranes & Derricks in Construction, Anti Two-Block
tip (or fixed upper block or similar component) must be used. The device(s) must prevent such damage/failure at all points where two-blocking could ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(d) Equipment Criteria > 1926.1431(d)(5) Devices > 1926.1431(d)(5)(v) Anti Two-Block
1926.1416(d)(3) Cranes & Derricks in Construction, Anti Two-Blocking Device
such damage at all points where two-blocking could occur.
Temporary alternative measures: Clearly mark the cable (so that it can easily be seen ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1416 Operational Aids > 1926.1416(d) Category I Operational Aids and Alternative Measures > 1926.1416(d)(3) Anti Two-Blocking Device
1926.1435(e)(5)(iii) Cranes & Derricks in Construction, Anti Two-Blocking Device
component, and the boom tip (or fixed upper block or similar component). The device(s) must prevent such damage at all points where two-blocking could ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1435 Tower Cranes > 1926.1435(e) Operational Aids > 1926.1435(e)(5) Category I Operational Aids and Alternative Measures > 1926.1435(e)(5)(iii) Anti Two-Blocking Device
1926.1436(g)(2)(iv) Cranes & Derricks in Construction,
Actuating the anti two-block and boom hoist limit devices (if provided) ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1436 Derricks > 1926.1436(g) Post-Assembly Approval and Testing--New or Reinstalled Derricks > 1926.1436(g)(2) Functional Test > 1926.1436(g)(2)(iv)