G105.2 All Work Applications
JUMP TO FULL CODE CHAPTER
All work applications, regardless of the extent of the scope of work, shall be subject to the following special inspection:
- Flood zone compliance inspection. Prior to sign-off of work, a registered design professional shall certify that: "the structure was constructed" or "alterations were performed," "with methods and practices that minimize flood damage and that are in accordance with approved plans, and with any applicable provisions of Appendix G of the New York City Building Code and ASCE 24."
Related Code Sections
G105.2 Flood-Resistant Construction, All Work Applications
All work applications, regardless of the extent of the scope of work, shall be subject to the following special inspection ...
NYC Building Code 2008 > G Flood-Resistant Construction > G105 Progress and Special Inspection Requirements > G105.2 All Work Applications
G105.2 Flood-Resistant Construction, All Work Applications Other Than New Buildings and Substantial Improvements
All work applications other than new buildings and substantial improvements, shall be subject to the following special inspection: 1. Flood zone ...
NYC Building Code 2014 > G Flood-Resistant Construction > G105 Progress and Special Inspection Requirements > G105.2 All Work Applications Other Than New Buildings and Substantial Improvements
G107.2 Flood-Resistant Construction, All Work Applications Other Than New Buildings, Horizontal Enlargements and Substantial Improvements
All work applications other than new buildings, horizontal
enlargements and substantial improvements, shall be subject to the following special ...
NYC Building Code 2022 > G Flood-Resistant Construction > G107 Periodic, Progress and Special Inspection Requirements > G107.2 All Work Applications Other Than New Buildings, Horizontal Enlargements and Substantial Improvements
§27-916 Plumbing and Gas Piping, General
for an extension in size or change in use in which plumbing, drainage, or gas piping work is involved, all the new work shall be made to conform to all ...
NYC 1968 Code (Vol I) > 16 Plumbing and Gas Piping > 6 Existing Buildings and Installations > §27-916 General
§28-104.2.1.5 Administration, Applicant Requirement
withdraws from the job before the issuance of a letter of completion or certificate of occupancy, as applicable, all work shall stop and no permit, letter ...
NYC General Admin. Provisions 2008 > 1 Administration > 104 Construction Documents > §28-104.2 Application for Approval of Construction Documents > §28-104.2.1 Less Than Full Examination of Construction Documents > §28-104.2.1.5 Applicant Requirement