C402.4.2 Air Barrier Penetrations
Go To Full Code Chapter
Penetrations of the air barrier and paths of air leakage shall be caulked, gasketed or otherwise sealed in a manner compatible with the construction materials and location. Joints and seals shall be sealed in the same manner or taped or covered with a moisture vapor-permeable wrapping material. Sealing materials shall be appropriate to the construction materials being sealed. The joints and seals shall be securely installed in or on the joint for its entire length so as not to dislodge, loosen or otherwise impair its ability to resist positive and negative pressure from wind, stack effect and mechanical ventilation.
Upcodes Diagrams
Related Code Sections
C402.4.2 [CE] Commercial Energy Efficiency, Air Barrier Penetrations
Penetrations of the air barrier and paths of air leakage shall be caulked, gasketed or otherwise sealed in a manner compatible with the construction ...
5.4.3.1.2 Building Envelope, Continuous Air Barrier Design and Installation
, interconnections, and penetrations of the continuous air barrier component shall be detailed in the construction documents.
The continuous air barrier shall ...
C402.5.1.1 [CE] Commercial Energy Efficiency, Air Barrier Construction
The continuous air barrier shall be constructed to comply with the following: The air barrier shall be continuous for all assemblies ...
6.7.3 Systems and Equipment, Smoke Barriers
Where smoke barriers are required, heating, ventilating, and air-conditioning zones shall be coordinated with compartmentation to minimize ductwork ...
6.7.3 Systems and Equipment, Smoke Barriers
Where smoke barriers are required, heating, ventilating, and air-conditioning zones shall be coordinated with compartmentation to minimize ductwork ...