3102F.4.7 Action Plan Report
JUMP TO FULL CODE CHAPTER
Upon completion of all actions delineated in the action plan, a final report shall be submitted to the Division to document the work completed. Supporting documentation such as calculations or other relevant data shall be provided in appendices.
Related Code Sections
3102F.4.7 [SLC] Marine Oil Terminals, Action Plan Report
Upon completion of all actions delineated in the action plan, a final report shall be submitted to the Division to document the work completed ...
Los Angeles Building Code > 31F [SLC] Marine Oil Terminals > 3102F Audit and Inspection > 3102F.4 Post-Event Inspection > 3102F.4.7 Action Plan Report
322.6 Provisions for All Compliance Methods, Response and Resolutions
The registered design professional shall review the report from the reviewer(s) and shall develop corrective actions and responses as appropriate ...
Los Angeles Existing Building Code > 3 Provisions for All Compliance Methods > 322 Peer Review Requirements > 322.6 Response and Resolutions
322.6 Provisions for All Compliance Methods, Response and Resolutions
The registered design professional shall review the report from the reviewer(s) and shall develop corrective actions and responses as appropriate ...