510.5.3 Acceptance Test Procedure
JUMP TO FULL CODE CHAPTER
Where an emergency responder radio coverage system is required, and upon completion of installation, the building owner shall have the radio system tested to verify that two-way coverage on each floor of the building is not less than 95 percent. The test procedure shall be conducted as follows:
- Each floor of the building shall be divided into a grid of 20 approximately equal test areas.
- The test shall be conducted using a calibrated portable radio of the latest brand and model used by the agency talking through the agency's radio communications system or equipment approved by the fire code official.
- Failure of more than one test area shall result in failure of the test.
- In the event that two of the test areas fail the test, in order to be more statistically accurate, the floor shall be permitted to be divided into 40 equal test areas. Failure of not more than two nonadjacent test areas shall not result in failure of the test. If the system fails the 40-area test, the system shall be altered to meet the 95-percent coverage requirement.
- A test location approximately in the center of each test area shall be selected for the test, with the radio enabled to verify two-way communications to and from the outside of the building through the public agency's radio communications system. Once the test location has been selected, that location shall represent the entire test area. Failure in the selected test location shall be considered to be a failure of that test area. Additional test locations shall not be permitted.
- The gain values of all amplifiers shall be measured and the test measurement results shall be kept on file with the building owner so that the measurements can be verified during annual tests. In the event that the measurement results become lost, the building owner shall be required to rerun the acceptance test to reestablish the gain values.
- As part of the installation, a spectrum analyzer or other suitable test equipment shall be utilized to ensure spurious oscillations are not being generated by the subject signal booster. This test shall be conducted at the time of installation and at subsequent annual inspections.
- Systems incorporating Class B signal-booster devices or Class B broadband fiber remote devices shall be tested using two portable radios simultaneously conducting subjective voice quality checks. One portable radio shall be positioned not greater than 10 feet (3048 mm) from the indoor antenna. The second portable radio shall be positioned at a distance that represents the farthest distance from any indoor antenna. With both portable radios simultaneously keyed up on different frequencies within the same band, subjective audio testing shall be conducted and comply with DAQ levels as specified in Sections 510.4.1.1 and 510.4.1.2.
Related Code Sections
510.5.3 Fire Service Features, Acceptance Test Procedure
tested to verify that two-way coverage on each floor of the building is not less than 95 percent. The test procedure shall be conducted as follows ...
Fire Code 2018 of Colorado > 5 Fire Service Features > 510 Emergency Responder Radio Coverage > 510.5 Installation Requirements > 510.5.3 Acceptance Test Procedure
510.5.4 Fire Service Features, Acceptance Test Procedure
procedure shall be conducted as follows: Each floor of the building shall be divided into a grid of 20 approximately equal test areas. The test shall ...
Fire Code 2021 of Colorado > 5 Fire Service Features > 510 Emergency Responder Communication Coverage > 510.5 Installation Requirements > 510.5.4 Acceptance Test Procedure
14.4.10.5* Inspection, Testing, and Maintenance, Acceptance Test
An acceptance test of the public safety radio enhancement system shall be scheduled with the authority having jurisdiction. Acceptance test ...
National Fire Alarm and Signaling Code 2013 of Colorado > 14 Inspection, Testing, and Maintenance > 14.4 Testing > 14.4.10* In-Building Emergency Radio Communication Systems > 14.4.10.5* Acceptance Test
1708.3.1 Special Inspections and Tests, Load Test Procedure Specified
Where a referenced standard contains an applicable load test procedure and acceptance criteria, the test procedure and acceptance criteria ...
Building Code of the Department of Personnel & Administration/Office of the State Architect (DPA/OSA) > 17 Special Inspections and Tests > 1708 In-Situ Load Tests > 1708.3 In-Situ Load Tests > 1708.3.1 Load Test Procedure Specified
1708.2.1 Special Inspections and Tests, Load Test Procedure Specified
Where a referenced material standard contains an applicable load test procedure and acceptance criteria, the test procedure and acceptance criteria ...
Building Code 2021 of Colorado > 17 Special Inspections and Tests > 1708 In-Situ Load Tests > 1708.2 In-Situ Load Tests > 1708.2.1 Load Test Procedure Specified