C408.2.4.1 Acceptance of Report
JUMP TO FULL CODE CHAPTER
Buildings, or portions thereof, shall not be considered as acceptable for a final inspection pursuant to Section C105.2.6 until the code official has received the Preliminary Commissioning Report from the building owner or owner's authorized agent.
Related Code Sections
C408.2.4.1 [CE] Commercial Energy Efficiency, Acceptance of Report
Buildings, or portions thereof, shall not be considered as acceptable for a final inspection pursuant to Section C105.2.6 until the code official ...
2018 Philadelphia Energy Conservation Code > 4 [CE] Commercial Energy Efficiency > C408 Maintenance Information and System Commissioning > C408.2 Mechanical Systems and Service Water-Heating Systems Commissioning and Completion Requirements > C408.2.4 Preliminary Commissioning Report > C408.2.4.1 Acceptance of Report
806.4 Interior Finishes, Acceptance Criteria and Reports
701, or exhibit a maximum heat release rate of 100 kW when tested in accordance with NFPA 289, using the 20 kW ignition source. Reports of test ...
2018 Philadelphia Building Code > 8 Interior Finishes > 806 Decorative Materials and Trim > 806.4 Acceptance Criteria and Reports
807.3 Interior Finish, Decorative Materials and Furnishings, Acceptance Criteria and Reports
source. Reports of test results shall be prepared in accordance with the test method used and furnished to the fire code official upon request ...
2018 Philadelphia Fire Code > 8 Interior Finish, Decorative Materials and Furnishings > 807 Decorative Materials and Artificial Decorative Vegetation in New and Existing Buildings > 807.3 Acceptance Criteria and Reports
1709.1 Special Inspections and Tests, General
to the tests prescribed in Section 1709. The building official shall accept certified reports of such tests conducted by an approved testing agency ...
2018 Philadelphia Building Code > 17 Special Inspections and Tests > 1709 Preconstruction Load Tests > 1709.1 General